Mill and Overlay Projects to Begin May 14

MILL AND OVERLAY PROJECT TO BEGIN MAY 14


A project to mill and overlay three City streets will begin on May 14, 2019. The City has a contract with Evans and Associates Construction Company to perform the work on Grand Avenue, Flormable Avenue to Waverly Street; Union Street at the Highland Avenue overpass; and El Camino Street, Prospect Avenue to Chapel Hill Road.

  1. Work will begin on Grand Avenue, Flormable Avenue to Waverly Street, on May 14. Grand Avenue will have the top 2 ½ inches of asphalt removed and replaced and is expected to take one week to complete.

  2. Next, work will take place on Union Street at the Highland Avenue overpass. The existing surface will be removed to the concrete deck and then overlaid with one inch of asphalt. Following the overlay the bridge deck joints will be re-sealed. The overpass will be closed to traffic briefly during the milling and overlay processes and for up to one full day for the joint sealing work.

  3. Finally, work on El Camino Street, Prospect Avenue to Chapel Hill Road, is anticipated to begin between May 22 and May 24. El Camino Street will have an average of 3 1/4 inches of asphalt removed and replaced and will take approximately 10 days to complete.

Hand bills will be distributed in affected neighborhoods prior to work beginning on the individual streets.

Questions pertaining to this project may be directed to Mike Lane, Traffic Engineering Manager, at 580-767-0327.